Celje, August 6, 2019 –All construction work carried out at the Vonarje Dam within the framework of the Frisco 2.1 project run smoothly and according to timetables. Slovenian contractor NIVO EKO d.o.o has already done most of his work, and a consortium of four Croatian companies is even doing faster than it is planned in particular works. On the Croatian side, the consortium is currently repairing worn-out concrete barrier. In addition, used metal barriers and equipment to manage them will be replacing. Accelerographs, piezometers and inclinometers, which are already installed on the Slovenian side, will be installed on Croatian side now too.